Samantha and Mark are discussing about Risk Burndown Chart and Risk Burnup Chart, their utilities, their pros and cons and where each of them should be used. Next they discuss how to identify problems using Risk Burndown Chart. What is the ideal trend that should be there in an Agile project's Risk burn down chart?
Risk Burndown Chart consists of a risk line which is the sum total of the risk exposures of all the risks that were taken while creating the burndown chart. The cumulative risks should decline and not move upwards. A sharp decline tells that the risks are being managed early and quickly in the cycle
By providing a telephone number and submitting this form you are consenting to be contacted by SMS text message. Message & data rates may apply. You can reply STOP to opt-out of further messaging.
Feel free to reach out to our representative: Yogita Bargaiya (+91 77953 71437)
Would you like a free ECO Tool that can help you revise the entire PMP syllabus in ONE hour?
By providing a telephone number and submitting this form you are consenting to be contacted by SMS text message. Message & data rates may apply. You can reply STOP to opt-out of further messaging.